|

Welcome to our 2012 project blog where you will be able to follow us and gain an insight into the work of one our Lancashire dry stone walling teams, in their work on a dry stone walling heritage restoration project..
We will be providing a monthly blog feature on one of our grant funded Heritage Stonework Restoration Projects for dry stone walling in lancashire- phase 1.
More information on our grant funding scheme for dry stone walls is available ...
Read more...
Dry Stone Walling Heritage Restoration Works Description
Context: Heritage restoration, Private Grant funded
Dry stone walling in Lancashire
Phase: 1 (of 5). phase 1 is one of five dry stone wall restoration projects
making up a whole farm walls restoration.: N1:N6
Location: Hoghton, Preston. Lancashire
Purpose: Agricultural Stock Wall
Date constructed: 1841
Rebuild Commencement: 25/01/12
Length: Phase 1: N1:N2. three hundred and twenty two metres
Height: 1.6m
Stone type: Gritstone
Copestones: half moon, hand masoned
Condition assessment: phase 1: N1 to N2. Major slumping and bulging/ bellying, approximately
86% copestones on site or on wall. Structure: standard build. Foundations 78% secure. Tree growth in/at wall: 7 elder, three hawthorn - invasive.
Contract: Total rebuild N1:N6
Grant funding allocation: (phase 1: N1:N2) 56%
Other: N3 intersection (phase 2)
Existing dry stone wall conditions of N1 to N2 at 12/11/11 more photos soon
 
Our Monthly Blog.... 
December 2011/ January 2012 .....
Most of December was spent in meetings and site visits with the landowner and everyone else connected to the project, followed by a lengthy mapping exercise in January for the Lancashire dry stone walls, where we mapped, photographed and condition assessed all the dry stone walls - phases 1 to 5, preparing our final report for mid January; this was followed by site specific risk assessments, local history research and further meetings with all concerned. It was 7.30am on the 25th January when we began works on phase 1, tree pruning, dismantling, sorting and grading a 20 metre section of dry stone wall, constructing and aligning precision wooden batter frames on site. We will be using batter frames and lines throughout the project as we will be working on long sections of dry stone wall and the completed works need to be as close as possible to the original construction. The weather, so far has been mild, although rain and high winds have been with us along with a very wet ground underfoot. Hopefully the relatively mild weather will continue as we progress with works into February. Our next blog will be towards the end of February.....

Dismantling Batter frame Tree pruning
February 2012 .....
Works are well underway...

Snapshot of works in progress - top of dry stone wall - section complete, levelled and beginning of alignment of copestones
Since our last blog we have made good progress with reconstructing 30 metres of Lancashire dry stone wall to original specification. The weather has been mixed, but generally good. During dismantling of the dry stone wall we discovered three bands of through stones which run the entire length of the stretch of wall. Two bands were recognisable by their throughstones protruding from the wall, but unusually the distance between the bands was just 12 inches; the third set of throughs were placed at 80% wall height, again in bands along the length of the entire wall, but not protruding - the top of the wall being capped by the half moon, hand masoned copestones.We will be meeting with a local historian later this month to discuss the significance of the wall. Many trees that were overhanging the dry stone wall have been pruned to enable easy access for us and agricultural machinery. Perhaps the highlights of this month was a visit from the building skills heritage folk to see how one of our apprentices was getting on and also, around 7.20 am on a frosty morning, a stoat in its white winter coat scampered along a series of copestones on the wall in front of us whilst we were drinking coffee! In march we hope to tackle a longer stretch of dry stone wall and place and pin copestones to the finished section. Our next blog will be towards the end of march and we will be adding some photos for february here soon....

March
Most of this month we have spent alot of time on wet marsh ground, removing and setting new foundations for the next 40 metres rebuild of dry stone wall. Amongst stripping out the wall and grading stone, we restored some 56 copestones and all were placed on the levelled dry stone wall in one day, despite their heavy weight. Mid march to 26th march, our team undertook two weeks of professional development, where we took time away from work on the wall to spend some time with a stonemasonry company in wales. During the time we were away, our second team of dry stone wallers undertook further restoration of copestones on the dry stone wall and the works to date were opened for two days for visitors in the local area. We are now starting to rebuild the next 40 metres and with the hot, dry weather set to continue and more light in the evenings, we will hopefully achieve next months targets. Finds from inside the dry stone wall in March have included clay pipes, old coins, copper buttons, a whisky flask and a few old bottles with marbles inside.
 

left. copestone separation (mortar removal). Above. finished south facing wall at 20 m.
Below: final mortar removal before placing
April

snapshot - final levelling before placing copestones
Early to mid April works have been slower due to the continuation of resetting foundation stones and a shortage of hearting stone, alot of which had decayed over the years; thankfully a trailer load of rubble stone was supplied and we are now continuing to pick up pace again. April 15th saw us stop work for around ten minutes as we watched two hares chasing and 'boxing', making their way around the field at speed and then up and over the 1.6m dry stone wall , into the woodland behind. Four buzzards continue to circle, mid morning each day above us looking for still born lambs and we now have a robin each morning, perched on our batter frame waiting for insects near the dry stone wall. We will be raising a high visibility safety line with small tabs at 12 inches above our finished dry stone walling works, as towards the end of April, early one morning three adult roe deer jumped over the wall whilst we were setting levels at ground level on the other side! Water continues to accumilate underfoot as the weather is still rather wet, despite the warm spell a few weeks ago. The Heritage folk will be visiting us again in May along with a few local landowners.

Two bands of throughstones placed
as in the original dry stone wall
Dry stone walling contractor Lancashire, grants for dry stone walling, grants for dry stone walling in lancashire, grants for dry stone walling in preston, grants for dry stone walling in manchester, grants for dry stone walling in cumbria, grants for dry stone walling in uk, dry stone wall repair contractor, build a dry stone wall, dry stone walling preston...
|